17 July 2024
8 July 2024
22 July 2024
1 June 2024
23 May 2024
30 May 2024
16 May 2024
27 April 2024
12 April 2024
15 April 2024
29 April 2024
26 April 2024
3 April 2024
9 April 2024
10 October 2023
17 January 2023
11 November 2022
The results from the land investigations conducted by Coff ey principal geotechnical engineer Peter Marchant (far right) and Coff ey engineering geologist Matt Illingworth for McConnell Dowell will provide a picture of the sub-soil conditions and nature of the ground where structures will be constructed at each water intake site as part of the Te Mato Vai Stage 2 project. 17110312
Land investigation work at the 10 Rarotonga water intake sites marked for upgrades under the Te Mato Vai Stage 2 project has been completed.
CLICK HERE TO SUBSCRIBE NOW
for as little as $11 per month.
- Up to date and breaking news
- Includes access to Premium content
- Videos and online classifieds
Already a subscriber, click here