Repairs for town road

Thursday September 13, 2018 Written by Published in Local
Traffic has been reduced to one lane on the lagoon side of the main road in town while road damage is repaired. 18091113 Traffic has been reduced to one lane on the lagoon side of the main road in town while road damage is repaired. 18091113

Contractor Triad continued with road maintenance and repair works on behalf of ICI on the lagoon side of Maire Nui Drive in Avarua yesterday.

ICI engineer Gareth Clayton said the roadworks were designed to improve the safety and durability of a section of damaged road.

“The works involve clearing of existing drainage and pavement excavation to confirm the cause of the damage,” he said.

“The repair treatment will include installation of subsoil pavement drainage, pavement construction including stabilised basecourse and a temporary surfacing. 

“The final surfacing will be installed at a later date following trafficking of the surface.”